Aggregating planned works across 100 buildings · 2,000 lots. Use clusters to bundle like-for-like works into one tender — e.g. ten buildings re-painting in the same window become a single procurement event.
10-yr portfolio spend
$141.3M
Peak 2028: $24.3M
Buildings with planned works
100
3,566 line items
Procurement clusters
106
106 high-value tender opps
Buildings in scope
100
From current filter
Demand by year
Click a year to filter clusters below
Category × year heatmap
Darker cells signal concentration — good candidates for bundled tender
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
Fire & Safety
Mechanical
Electrical
Structural / Envelope
Aesthetic
Amenity
Grounds
Filters:106 procurement opportunities
Procurement clusters
Asset + year combinations that can be tendered together
Asset
Category
Year
Buildings
Total est.
Avg per bldg
Tender opportunity
Fire hydrant & sprinkler 5yr test
Fire & Safety
2033
100
$1.8M
$18k
High — bundle now
Fire hydrant & sprinkler 5yr test
Fire & Safety
2028
100
$1.6M
$16k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2035
100
$349k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2034
100
$341k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2033
100
$332k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2032
100
$324k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2031
100
$315k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2030
100
$307k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2029
100
$298k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2028
100
$290k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2027
100
$281k
$3k
High — bundle now
Annual Fire Safety Statement (AFSS)
Fire & Safety
2026
100
$273k
$3k
High — bundle now
Common-area LED conversion
Electrical
2026
58
$987k
$17k
High — bundle now
Common-area LED conversion
Electrical
2027
41
$694k
$17k
High — bundle now
Fire pump replacement
Fire & Safety
2032
40
$2.8M
$70k
High — bundle now
Smoke detection & EWIS upgrade
Fire & Safety
2029
36
$1.9M
$54k
High — bundle now
Smoke detection & EWIS upgrade
Fire & Safety
2028
35
$1.9M
$54k
High — bundle now
Fire pump replacement
Fire & Safety
2031
34
$2.4M
$72k
High — bundle now
Garden hardscape & irrigation
Grounds
2030
34
$1.0M
$30k
High — bundle now
Carpark line marking
Grounds
2028
33
$203k
$6k
High — bundle now
Pool heater & filtration
Amenity
2028
32
$749k
$23k
High — bundle now
Main switchboard upgrade
Electrical
2029
31
$2.4M
$79k
High — bundle now
Pool tile & coping
Amenity
2035
31
$2.3M
$75k
High — bundle now
Internal common-area painting
Aesthetic
2029
31
$1.1M
$36k
High — bundle now
Pool plant — pump #2
Amenity
2028
31
$223k
$7k
High — bundle now
HVAC — chiller plant
Mechanical
2032
29
$3.7M
$126k
High — bundle now
Smoke detection & EWIS upgrade
Fire & Safety
2030
29
$1.5M
$52k
High — bundle now
Lift B — major modernisation
Mechanical
2032
28
$4.8M
$171k
High — bundle now
Roof membrane replacement
Structural / Envelope
2032
28
$2.4M
$87k
High — bundle now
External painting
Aesthetic
2028
28
$2.1M
$77k
High — bundle now
Lobby refurbishment
Aesthetic
2027
28
$1.8M
$63k
High — bundle now
Internal common-area painting
Aesthetic
2030
28
$984k
$35k
High — bundle now
Roof membrane replacement
Structural / Envelope
2027
28
$435k
$16k
High — bundle now
HVAC — chiller plant
Mechanical
2027
28
$339k
$12k
High — bundle now
Carpark line marking
Grounds
2031
28
$183k
$7k
High — bundle now
Lift A — major modernisation
Mechanical
2029
27
$4.5M
$166k
High — bundle now
External painting
Aesthetic
2027
27
$2.1M
$77k
High — bundle now
Intercom / access control
Electrical
2029
27
$1.8M
$67k
High — bundle now
Intercom / access control
Electrical
2028
27
$1.8M
$67k
High — bundle now
EV charging infrastructure
Electrical
2030
27
$1.6M
$61k
High — bundle now
✨